Skip to main content.
Internal Audit Home > Audit Plan > FY 2010 Audit Plan

University of Mary Washington Audit Plan

July 1, 2009 through June 30, 2010

University of Mary Washington
Audit Plan
July 1, 2009 through June 30, 2010

 

HOURS

% OF TOTAL

AVAILABLE HOURS

2,080 100%

 

AUDITS

Cashier's Office

Fire Alarm

Health Center- Nuesoft

Psychological Services-Titanium

Follow-Up Status Report

Year End Inventory and Cash Counts

 

 

380

180

180

180

80

40

 

 

TOTAL FOR PLANNED AUDITS

1,040 50%

 

SPECIAL PROJECTS:

ARMICS Compliance

VITA Compliance

 

 

 

40

100

 

TOTAL FOR SPECIAL PROJECTS

140 7%
     
MANAGEMENT REQUESTS 250 12%

 

AUDIT RELATED:

Audit Plan and Risk Assessment

Board Meetings

Status Reports

Meetings with President's Office

 

 

80

40

4

10

 

 
TOTAL FOR AUDIT RELATED TASKS 134 6%
     

TOTAL AUDIT AND AUDIT RELATED HOURS

1,564 75%

 

ADMINISTRATIVE:

Annual/Sick/Other Leave

Training and Seminars

Holidays

Personnel and Office Administration


 

 

240

100

36

40

 
TOTAL FOR ADMINISTRATIVE TASKS 516 25%
     
TOTAL HOURS REMAINING - 0%